[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892489":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892489,578,2,"多选题","桩的检验荷载试验（暂定工程量）分不同的（ ）以每一试桩为单位计量。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","柱径",true,{"key":16,"text":17,"correct":14},"B","桩长",{"key":19,"text":20,"correct":21},"C","桩重",false,{"key":23,"text":24,"correct":14},"D","检验荷载等级",{"key":26,"text":27,"correct":14},"E","混凝土强度等级","ABDE","桩的检验荷载试验（暂定工程量）：依据图纸及柱的检验荷载试验委托合同，在图纸所示位置现场进行柱的检验荷载试验，按实际进行检验荷载试验的柱数，分不同的柱径、桩长、混凝土强度等级、检验荷载等级以每一试柱为单位计量。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]