[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892483":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892483,578,2,"多选题","清理现场计量的工程内容包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","灌木、竹林、胸径小于10cm树木的砍伐及挖根",true,{"key":16,"text":17,"correct":14},"B","与清理现场有关的一切挖方、坑穴的回填、整平、压实",{"key":19,"text":20,"correct":14},"C","适用材料的装卸、移运、堆放及非适用材料的移运处理",{"key":22,"text":23,"correct":24},"D","清除与清理现场有关的一切挖方地表面20～50cm范围内的垃圾",false,{"key":26,"text":27,"correct":14},"E","现场清理","ABCE","清理现场计量内容：①灌木、竹林、胸径小于10cm树木的砍伐及挖根；②清除场地表面0～30cm范围内的垃圾、废料、表土（腐殖土）、石头、草皮；③与清理现场有关的一切挖方、坑穴的回填、整平、压实；④适用材料的装卸、移运、堆放及非适用材料的移运处理；⑤现场清理。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]