[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892477":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892477,578,2,"多选题","编写工程量清单时需要注意的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","将开办项目作为独立的工程子目单列出",true,{"key":16,"text":17,"correct":14},"B","合理划分工程子目",{"key":19,"text":20,"correct":14},"C","工程量的计算整理要细致准确",{"key":22,"text":23,"correct":24},"D","计日工数量要注明",false,{"key":26,"text":27,"correct":24},"E","主要计量单位要准确","ABC","编写工程量清单时需要注意的有：①将开办项目作为独立的工程子目单列出；②合理划分工程子目；③工程子目的划分要大小合适；④工程量的计算整理要细致准确；⑤计日工清单或专项暂定金额不可缺少；⑥应与工程量清单计量规则一致。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]