[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892473":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892473,578,2,"多选题","竣工决算的编制步骤包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","收集、整理和分析有关依据资料",true,{"key":16,"text":17,"correct":14},"B","清理各项账务、债务和结余物资",{"key":19,"text":20,"correct":14},"C","填写竣工决算报表",{"key":22,"text":23,"correct":24},"D","编写建设工程量决算清单",false,{"key":26,"text":27,"correct":14},"E","上报主管部门审查编制竣工决算的程序","ABCE","竣工决算的编制步骤：①收集、整理和分析有关依据资料；②清理各项账务、债务和结余物资；③填写竣工决算报表；④编写建设工程竣工决算说明书；⑤上报主管部门审查编制竣工决算的程序。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]