[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892471":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892471,578,2,"多选题","关于进度付款证书和支付时间的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","如果该付款周期应结算的价款经扣留和扣回后的款额少于项目专用合同条款数据表中列明的进度付款证书的最低金额，则该付款周期监理工程师可不核证支付",true,{"key":16,"text":17,"correct":14},"B","发包人应在监理工程师收到进度付款申请单且承包人提交了合格的增值税专用发票后的28d内，将进度应付款支付给承包人",{"key":19,"text":20,"correct":21},"C","发包人不按期支付的，违约金计算基数为合同价",false,{"key":23,"text":24,"correct":21},"D","监理工程师出具进度付款证书，应视为监理人已同意、批准或接受了承包人完成的该部分工作",{"key":26,"text":27,"correct":14},"E","进度付款涉及政府投资资金的，按照国库集中支付等国家相关规定和专用合同条款的约定办理","ABE","C项，发包人不按期支付的，按项目专用合同条款数据表中约定的利率向承包人支付逾期付款违约金。违约金计算基数为发包人的全部未付款额，时间从应付而未付该款额之日算起（不计复利）。D项，监理工程师出具进度付款证书，不应视为监理人已同意、批准或接受了承包人完成的该部分工作。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]