[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892469":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892469,578,2,"多选题","按时间分类，支付可分为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预付",true,{"key":16,"text":17,"correct":14},"B","期中支付",{"key":19,"text":20,"correct":21},"C","交工决算",false,{"key":23,"text":24,"correct":14},"D","交工结算",{"key":26,"text":27,"correct":14},"E","最终结清","ABDE","按时间分类，支付可分为预先支付即预付、期中支付、交工结算、最终结清4种。 ①预付。预付款有两种，即开工预付款和材料预付款，是由业主提供给承包人的无息款项，按一定条件支付并扣回。 ②期中支付。期中支付款即进度款，按月支付，即按本月完成的工程价值及其他有关款项进行综合支付，由监理工程师开出期中支付证书来实施。 ③交工结算。交工结算即在项目完工或基本完工，监理工程师签发交工证书后办理的支付工作。 ④最终结清。最终结清即在缺陷责任期结束，监理工程师签发缺陷责任证书后，办理的最后一次支付工作。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]