[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892468":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892468,578,2,"多选题","采用计日工计价的任何一项变更工作，承包人应在变更的实施过程中，每天提交（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工作名称、内容和数量",true,{"key":16,"text":17,"correct":14},"B","投入该工作所有人员的姓名、工种、级别和耗用工时",{"key":19,"text":20,"correct":14},"C","投入该工作的材料类别和数量",{"key":22,"text":23,"correct":24},"D","承包单位提交的其他资料和凭证",false,{"key":26,"text":27,"correct":24},"E","工程的基本档案信息","ABC","采用计日工计价的任何一项变更工作，应从暂列金额中支付，承包人应在变更的实施过程中，每天提交以下报表和有关凭证报送监理工程师审批： ①工作名称、内容和数量； ②投入该工作所有人员的姓名、工种、级别和耗用工时； ③投入该工作的材料类别和数量； ④投入该工作的施工设备型号、台数和耗用台时； ⑤监理工程师要求提交的其他资料和凭证。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]