[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892467":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892467,578,2,"多选题","工程价款价差调整的主要方法包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实际文件评估法",false,{"key":16,"text":17,"correct":18},"B","调值公式法",true,{"key":20,"text":21,"correct":18},"C","实际价格调整法",{"key":23,"text":24,"correct":18},"D","调价文件计算法",{"key":26,"text":27,"correct":18},"E","工程造价指数调整法","BCDE","工程价款价差调整的主要方法：工程造价指数调整法、实际价格调整法、调价文件计算法和调值公式法。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]