[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892374,578,1,"单选题","路面结构层包括面层、垫层、基层、底基层，从上到下排序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","面层、基层、底基层、垫层",true,{"key":16,"text":17,"correct":18},"B","面层、垫层、基层、底基层",false,{"key":20,"text":21,"correct":18},"C","面层、垫层、底基层、基层",{"key":23,"text":24,"correct":18},"D","面层、基层、垫层、底基层","路面工程中，路面结构层自下而上依次为：垫层、底基层、基层、面层（下、中、上）。由此可知自上而下的结构层顺序为：面层、基层、底基层、垫层。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]