[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892353,578,1,"单选题","排水系统养护处治中，当土质边沟受水流冲刷造成纵坡大于（ ）时，宜采用混凝土、浆砌或干砌片（块）石铺砌。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2%",false,{"key":16,"text":17,"correct":18},"B","3%",true,{"key":20,"text":21,"correct":14},"C","5%",{"key":23,"text":24,"correct":14},"D","6%","当土质边沟受水流冲刷造成纵坡大于3%时，宜采用混凝土、浆砌或干砌片（块）石铺砌；冰冻较轻地区可采用稳定土加固。边沟连续长度过长时，宜分段设置横向排水沟将水流引离路基，其分段长度一般地区不超过500m，多雨地区不超过300m。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]