[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892347":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892347,578,1,"单选题","施工组织计划的内容不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程进度图",false,{"key":16,"text":17,"correct":14},"B","主要材料计划表",{"key":19,"text":20,"correct":14},"C","临时工程表",{"key":22,"text":23,"correct":24},"D","施工方案的修正",true,"不论工程采用几阶段设计，在施工图阶段都应编制施工组织计划，其内容包括：①说明；②工程进度图（包括劳动力计划安排）；③主要材料计划表（包括型号、规格及数量）；④主要施工机具、设备计划表；⑤临时工程表（包括通往工地、料场、仓库等的便道、便桥及电力、电信设施等）；⑥重点工程施工场地布置图；⑦重点工程施工进度图。D项，修正施工方案与施工组织计划同为施工组织设计的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]