[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892326,578,1,"单选题","路基施工前应做好的三大准备不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织",false,{"key":16,"text":17,"correct":14},"B","物资",{"key":19,"text":20,"correct":21},"C","合同",true,{"key":23,"text":24,"correct":14},"D","技术","路基施工前应做好组织、物资和技术三大准备。其中，技术准备是工程顺利实施的基础和保证，主要包括熟悉设计文件、现场调查核对、设计交桩、复测与放样、试验及试验路段施工等工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]