[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892322,578,1,"单选题","根据隧道穿越地层的不同情况和目前隧道施工技术的发展，山岭隧道的支护方法不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","新奥法",false,{"key":16,"text":17,"correct":18},"B","盖挖法",true,{"key":20,"text":21,"correct":14},"C","掘进机法",{"key":23,"text":24,"correct":14},"D","传统矿山法","隧道施工方法的选择主要依据地质、地形、环境条件及埋置深度，并结合隧道断面尺寸、长度、衬砌类型、隧道的使用功能和施工技术水平等因素综合考虑确定。山岭隧道的施工方法有传统矿山法、新奥法、掘进机法。浅埋及软土隧道的施工方法有明挖法、地下连续墙法、盖挖法、浅埋暗挖法、盾构法。水底隧道的施工方法有沉管法、盾构法。B项，盖挖法属于浅埋及软土隧道的施工方法。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]