[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892321":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892321,578,1,"单选题","悬索桥是跨越千米以上障碍物最理想的桥型，其施工的一般步骤为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","索塔、锚碇基础→索塔、锚碇→上部结构→桥面系",true,{"key":16,"text":17,"correct":18},"B","索塔、锚碇基础→上部结构→索塔、锚碇→桥面系",false,{"key":20,"text":21,"correct":18},"C","索塔、锚碇→索塔、锚碇基础→上部结构→桥面系",{"key":23,"text":24,"correct":18},"D","索塔、锚碇→索塔、锚碇基础→桥面系→上部结构","悬索桥施工步骤一般包括：①索塔、锚碇的基础工程施工，同时加工制造上部施工所需构件。②索塔、锚碇施工及上部施工准备。包括塔身及锚体施工、上部施工技术准备、机具和物资准备、预埋件等上部施工准备工作。③上部结构安装。即缆索系统安装，包括主、散索鞍安装，先导索施工，猫道架设，主缆架设，紧缆，索夹安装。吊索安装，主缆缠丝防护等。④桥面系施工。即加劲梁和桥面系施工，包括加劲梁节段安装、工地连接、桥面铺装、桥面系及附属工程施工、机电工程等。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]