[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892319,578,1,"单选题","关于斜拉桥的拉索施工，下列说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","张拉机具能力应大于最大拉索拉力",false,{"key":16,"text":17,"correct":18},"B","拉索可在塔端或梁端两侧进行张拉",true,{"key":20,"text":21,"correct":14},"C","索塔横桥向两侧张拉应对称同步进行",{"key":23,"text":24,"correct":14},"D","两侧不对称拉索应按设计规定的索力分级同步张拉","A项，施工配备的张拉机具能力应大于最大拉索所需要的张拉力。BC两项，拉索可在塔端或梁端单端进行张拉，张拉时应按索塔的顺桥向两侧及横桥向两侧对称同步进行。D项，两侧不对称或设计拉力不同的拉索，应按设计规定的索力分级同步张拉，各千斤顶同步之差不得大于油表读数的最小分格。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]