[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892317,578,1,"单选题","斜拉桥索塔的施工可视其结构、体形、材料、施工设备和设计综合考虑选用合适的方法。索塔现浇施工方法不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","翻模法",false,{"key":16,"text":17,"correct":14},"B","滑模法",{"key":19,"text":20,"correct":21},"C","悬拼法",true,{"key":23,"text":24,"correct":14},"D","爬模法","斜拉桥索塔现浇施工的方法主要包括：①翻模法，应用较早，施工简单，能保证几何尺寸，外观整清。但模板空翻转操作危险，沿海地区不宜用此法。②滑模法，施工速度快，劳动强度小，但技术要求高，施工控制复杂，外观质量较差，且易污染。一般倾斜度较大，预留孔道及埋件多的索塔不宜用此法。③爬模法，爬模兼有滑模和翻模的优势，使用斜拉桥一般索塔的施工。施工安全，质量可靠，修补方便。国内外大多采用此法。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]