[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892316":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892316,578,1,"单选题","关于桥梁上部结构预制安装施工，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当桥址为深谷、急流时采用缆索吊装法架设",false,{"key":16,"text":17,"correct":14},"B","海上长大桥梁的架设安装可采用浮吊架设法",{"key":19,"text":20,"correct":21},"C","30m跨径的陆上预制梁架设可采用自行式吊车",true,{"key":23,"text":24,"correct":14},"D","节段式预应力混凝土连续梁架设可采用逐孔拼装法","A项，缆索吊装法是指在桥台或桥台后方设立钢塔架，塔架上悬挂缆索，以缆索作为承重索进行架设安装，当桥址为深谷、急流等桥下净空不能利用时采用。B项，浮吊架设法一般适用于河口、海上长大桥梁的架设安装，包括整孔架设和节段式块件的悬臂拼装。C项，跨径小于25m的陆上预制梁，结合地形条件可采用吨位符合要求的自行式吊车架设。跨径大于或等于25m的梁宜使用架桥机、跨墩龙门架或其他适合的专用大型机具设备。D项，逐孔拼装法一般适用于节段式预应力混凝土连续梁的施工。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]