[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892315,578,1,"单选题","下列关于预应力张拉的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先张法台座的锚固横梁受力后挠度不大于5mm",false,{"key":16,"text":17,"correct":14},"B","实际伸长值与理论伸长值的差值为5%时应暂停张拉",{"key":19,"text":20,"correct":21},"C","实施张拉时千斤顶与锚具的中心线应位于同一轴线上",true,{"key":23,"text":24,"correct":14},"D","未防腐的预应力筋安装后至压浆的容许间隔时间为7天","A项，先张法的墩式台座的锚固横梁受力后挠度不大于2mm；B项，预应力钢筋采用应力控制方法张拉时，实际伸长值与理论伸长值的差值应控制在±6%以内，否则应暂停张拉，查明原因并调整；C项，实施张拉时，千斤顶与预应力钢筋、锚具的中心线应位于同一轴线上；D项，未采取防腐措施的预应力钢筋，当空气湿度大于70%时，在安装后至压浆时的容许间隔时间为7天。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]