[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892298,578,1,"单选题","挖方路基施工中，土质路堑的施工工艺中包括：①路槽整修；②开挖截水沟；③边坡修理；④开挖边沟。正确的排序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②—①—④—③",false,{"key":16,"text":17,"correct":18},"B","②—③—④—①",true,{"key":20,"text":21,"correct":14},"C","①—②—③—④",{"key":23,"text":24,"correct":14},"D","①—③—②—④","挖方路基施工中，土质路堑的施工工艺流程如图1-3-1所示。由图可知正确顺序为：②—③—④—①。 图1-3-1 土质路堑施工工艺流程图",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]