[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892295,578,1,"单选题","二次衬砌是隧道工程施工在初期支护内侧施作的模筑混凝土或钢筋混凝土衬砌，二次衬砌施作时间应满足的条件不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","位移率明显减缓并已基本稳定",false,{"key":16,"text":17,"correct":14},"B","拱顶下沉速率小于0.07～0.15mm\u002F天",{"key":19,"text":20,"correct":21},"C","周边位移速率小于0.05～0.25mm\u002F天",true,{"key":23,"text":24,"correct":14},"D","已产生位移已达预计位移量的80%～90%","二次衬砌的应在初期支护变形基本稳定后进行，施作时间应满足下列条件：①各测试项目所显示的位移率明显减缓并已基本稳定。②已产生的各项位移已达预计位移量的80%～90%。③周边位移速率小于0.1～0.2mm\u002F天，或拱顶下沉速率小于0.07～0.15mm\u002F天。在满足上述条件后，应尽快进行二次衬砌的施作。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]