[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892293":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892293,578,1,"单选题","超前支护措施的选用应视围岩条件、涌水状况、施工方法、环境要求等情况而定，适用于围岩压力来得快、来得大的支护方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超前锚杆",false,{"key":16,"text":17,"correct":18},"B","管棚支护",true,{"key":20,"text":21,"correct":14},"C","预注浆方法",{"key":23,"text":24,"correct":14},"D","超前小导管","超前支护措施主要有：①超前锚杆或超前小导管支护主要适用于地下水较少的软弱破碎围岩的隧道工程中。②管棚主要适用于围岩压力来得快、来得大，用于对围岩变形及地表下沉有较严格限制要求的软弱破碎围岩隧道工程中。③超前小导管注浆不仅适用于一般软弱破碎围岩，也适用于地下水丰富的松软围岩。但超前小导管注浆对围岩加同的范围和强度是有限的。④预注浆方法是在掌子面前方的围岩中将浆液注入，从而提高地层的强度、稳定性和抗渗性，形成较大范闱的筒状封闭加固区，然后在其范围内进行开挖作业。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]