[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892292,578,1,"单选题","隧道洞口与明洞工程应按照隧道施工组织设计的顺序安排，按设计要求应先施工完成，下列关于洞口和明洞工程施工的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","洞口土石方开挖可采用大爆破以缩短工期",false,{"key":16,"text":17,"correct":18},"B","洞门端墙的砌筑与墙背回填应两侧同时进行",true,{"key":20,"text":21,"correct":14},"C","明洞段顶部回填土方每层厚度不得小于0.3m",{"key":23,"text":24,"correct":14},"D","当明洞与暗洞衔接时，施工宜采用先墙后拱法","A项，洞口土石方在洞口施工放样的线位上进行边坡、仰坡自上而下的开挖，不得采用大爆破，尽量减少对原地层的扰动。B项，洞门端墙的砌筑（或浇筑）与墙背回填应两侧同时进行，防止对衬砌产生偏压。C项，明洞施工一般采用先墙后拱法。当边坡松软易坍塌及明洞与暗洞衔接时，施工宜采用先拱后墙法。D项，明洞段顶部回填土方应对称分层夯实，每层厚度不得大于0.3m，两侧回填的土面高差不得大于0.5m。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]