[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892289,578,1,"单选题","新奥法施工过程不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开挖",false,{"key":16,"text":17,"correct":14},"B","喷锚",{"key":19,"text":20,"correct":21},"C","打锚杆",true,{"key":23,"text":24,"correct":14},"D","模筑混凝土","新奥法施工可划分为开挖、喷锚（初期支护）、模筑混凝土（二次衬砌）和装饰4个过程。其施工过程主要是开挖、喷锚、模筑混凝土三大工序的循环式流水作业，装饰是整个隧道贯通之后才进行的。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]