[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892287,578,1,"单选题","桥梁上部结构的施工方法的种类较多，大致可分为预制安装和现浇两大类，预制安装类不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预制梁安装",false,{"key":16,"text":17,"correct":14},"B","预制节段式块件",{"key":19,"text":20,"correct":14},"C","整跨箱梁预制吊装",{"key":22,"text":23,"correct":24},"D","预制桥墩、桥台安装",true,"预制安装可分为：①预制梁安装，主要指装配式的简支梁板进行横向联结或施工桥面板而使之成为桥梁整体；②预制节段式块件拼装，将梁体（一般为箱梁）沿桥轴向分段预制成节段式块件，运到现场进行拼装；③整跨箱梁预制吊装，通过在现场设置临时预制场将箱梁集中预制，大规模生产，然后利用大吨位运架机械逐跨架设。D项，预制墩台安装属于下部结构的预制拼装，不属于上部结构的施工。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]