[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892283,578,1,"单选题","下列关于钢筋笼吊装和混凝土灌注的说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","导管的埋置深度宜控制在2～4m",false,{"key":16,"text":17,"correct":14},"B","安装钢筋骨架时可接将钢筋骨架支承在孔底",{"key":19,"text":20,"correct":21},"C","钢筋笼骨架外侧设置应控制保护层厚度的垫块",true,{"key":23,"text":24,"correct":14},"D","当桩径D＜1.5m时，其坍落度宜为160～200mm","A项，在灌注中，应保持孔内的水头高度，导管的埋置深度宜控制在2～6m，并应随时测探孔内混凝土面的位置，及时调整导管埋深。B项，安装钢筋骨架时，应将其吊挂在孔口的钢护筒上，不得直接将钢筋骨架支承在孔底。C项，钢筋笼骨架外侧设置控制保护层厚度的垫块，其间距竖向为2m，横向圆周不得少于4处。D项，当桩径D＜1.5m时，其坍落度宜为180～220mm；桩径D＞1.5m时，坍落度宜为160～200mm。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]