[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892281,578,1,"单选题","关于挖基施工和排水，下列说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","挖基施工宜安排在枯水季节进行",false,{"key":16,"text":17,"correct":14},"B","排水困难时，宜采用水下挖基方法",{"key":19,"text":20,"correct":14},"C","挖至基底前预留一定厚度由人工开挖至设计高程",{"key":22,"text":23,"correct":24},"D","采用机械开挖时发现超挖，应直接回填至设计标高",true,"A项，挖基施工宜安排在枯水或少雨季节进行。B项，在开挖过程中进行排水时应不对基坑的安全产生影响，排水困难时，宜采用水下挖基方法。C项，采用机械开挖时宜在挖至基底前预留一定厚度，再由人工开挖至设计高程。D项，开挖过程中应避免超挖，如果超挖，应清除松动部分，并应对基底进行处理，不可直接回填。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]