[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892278,578,1,"单选题","下列关于后张法的张拉和锚固的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预应力张拉前应进行摩阻测试",false,{"key":16,"text":17,"correct":14},"B","直线筋或螺纹筋可在一端张拉",{"key":19,"text":20,"correct":21},"C","预应力钢筋张拉锚固后应在24h内完成压浆",true,{"key":23,"text":24,"correct":14},"D","切割后预应力钢筋的外露长度不应小于30mm","A项，预应力张拉前，宜对不同类型的孔道进行至少一个孔道的摩阻测试；B项，直线筋或螺纹筋可在一端张拉，对曲线预应力钢筋，当锚固损失的影响长度小于或等于构件长度的一半时，应采取两端同时张拉；C项，预应力钢筋张拉锚固后，孔道应尽早压浆，且应在48h内完成；D项，切割后预应力钢筋的外露长度不应小于30mm，锚具应采用封端混凝土保护。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]