[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892275,578,1,"单选题","后张法预制梁板施工时，当预制梁跨大于（ ）时，要按规定设置反拱。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10m",false,{"key":16,"text":17,"correct":14},"B","15m",{"key":19,"text":20,"correct":21},"C","20m",true,{"key":23,"text":24,"correct":14},"D","25m","根据预制梁的尺寸、数量、工期，确定预制台座的数量、尺寸，台座用表面压光的梁（板）筑成，应坚固不沉陷，确保底模沉降≤2mm，台座上铺钢板底模或用角钢镶边代作底模。当预制梁跨大于20m时，要按规定设置反拱。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]