[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892255,578,1,"单选题","隧道工程工程量清单计量中，以下不另行计量的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","洞身开挖",false,{"key":16,"text":17,"correct":18},"B","核对图纸",true,{"key":20,"text":21,"correct":14},"C","明洞工程",{"key":23,"text":24,"correct":14},"D","洞身衬砌","场地布置，核对图纸、补充调查、编制施工组织设计、试验检测、施工测量、环境保护、安全措施、施工防排水、围岩类别划分及监控、通信、照明、通风、消防等设备、设施预埋构件设置与保护，所有准备工作和施工中应采取的措施均为各节、各细目工程的附属工作，不另行计量。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]