[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892248":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892248,578,1,"单选题","石灰稳定土基层计量的工程内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","清理下承层",false,{"key":16,"text":17,"correct":14},"B","拌和",{"key":19,"text":20,"correct":21},"C","清除路基上的浮土",true,{"key":23,"text":24,"correct":14},"D","初期养护","石灰稳定土基层计量的工程内容包括：①检查、清理下承层、洒水；②拌和、运输、摊铺；③整平、整形；④洒水、碾压、初期养护。C项属于垫层计量的工程内容。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]