[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892236,578,1,"单选题","暂列金额的设置不宜超过工程量清单第100～700章合计金额的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3%",true,{"key":16,"text":17,"correct":18},"B","5%",false,{"key":20,"text":21,"correct":18},"C","10%",{"key":23,"text":24,"correct":18},"D","12%","工程量清单汇总表是将各章的工程子日表及计日工明细表进行汇总，再加上一定比例或数量（按招标文件规定）的暂列金额而得出项目的总报价，该报价与投标书中填写的投标总价是一致的，暂列金额的设置不宜超过工程量清单第100～700章合计金额的3%。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]