[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892231,578,1,"单选题","新增固定资产价值是以独立发挥生产能力的（ ）为对象。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程",false,{"key":16,"text":17,"correct":14},"B","分部工程",{"key":19,"text":20,"correct":14},"C","单位工程",{"key":22,"text":23,"correct":24},"D","单项工程",true,"新增固定资产价值是以独立发挥生产能力的单项工程为对象的。单项工程建成经有关部门验收鉴定合格，正式移交生产或使用，即应计算新增固定资产价值。一次交付生产或使用的工程一次计算新增固定资产价值，分期分批交付生产或使用的工程，应分期分批计算新增固定资产价值。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]