[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892226,578,1,"单选题","关于质量保证金的支付与返还的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","交工验收证书签发后14d内，承包人应向发包人缴纳质量保证金",false,{"key":16,"text":17,"correct":14},"B","质量保证金可采用银行保函或现金、支票形式",{"key":19,"text":20,"correct":21},"C","质量保证金采用现金、支票形式提交的，发包人应在项目通用合同条款数据表中明确是否计付利息以及利息的计算方式",true,{"key":23,"text":24,"correct":14},"D","保证金预留比率不得高于工程价款结算总额的3%","交工验收证书签发后14d内，承包人应向发包人缴纳质量保证金。质量保证金可采用银行保函或现金、支票形式，金额应符合项目专用合同条款数据表的规定。采用银行保函时，出具保函的银行须具有相应担保能力，且按照发包人批准的格式出具，所需费用由承包人承担。质量保证金采用现金、支票形式提交的，发包人应在项目专用合同条款数据表中明确是否计付利息以及利息的计算方式。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]