[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892225,578,1,"单选题","监理人在收到承包人进度付款申请单以及相应的支持性证明文件后的（ ）内完成核查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7d",false,{"key":16,"text":17,"correct":18},"B","14d",true,{"key":20,"text":21,"correct":14},"C","28d",{"key":23,"text":24,"correct":14},"D","30d","监理人在收到承包人进度付款申请单以及相应的支持性证明文件后的14d内完成核查，提出发包人到期应支付给承包人的金额以及相应的支持性材料，经发包人审查同意后，由监理工程师向承包人出具经发包人签认的进度付款证书。监理工程师有权扣发承包人未能按照合同要求履行任何工作或义务的相应金额。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]