[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892224":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892224,578,1,"单选题","材料、设备预付款按项目（ ）数据表中所列主要材料、设备单据费用的百分比支付。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专用合同条款",true,{"key":16,"text":17,"correct":18},"B","通用合同条款",false,{"key":20,"text":21,"correct":18},"C","工程量清单",{"key":23,"text":24,"correct":18},"D","协议书","材料、设备预付款按项目专用合同条款数据表中所列主要材料、设备单据费用（进口的材料、设备为到岸价，国内采购的为出厂价或销售价，地方材料为堆场价）的百分比支付。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]