[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892219":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892219,578,1,"单选题","公路工程工程量清单计价应采用（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合单价",false,{"key":16,"text":17,"correct":14},"B","工料单价",{"key":19,"text":20,"correct":21},"C","全费用综合单价",true,{"key":23,"text":24,"correct":14},"D","定额单价","公路工程工程量清单计价应采用“全费用综合单价”计价（又称全部综合单价），全费用综合单价包括为实施和完成合同工程所需的劳务、材料、机械、质检（自检）、安装、缺陷修复、管理、保险、税费、利润等费用，以及合同明示或暗示的所有责任、义务和一般风险。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]