[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892217,578,1,"单选题","关于计日工说明的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计日工不调价",false,{"key":16,"text":17,"correct":14},"B","投标人应在计日工单价表中填列计日工子目的基本单价或租价",{"key":19,"text":20,"correct":14},"C","未经监理人书面指令，任何工程不得按计日工施工",{"key":22,"text":23,"correct":24},"D","接到监理工程师按计日工施工的书面指令，承包人可以拒绝",true,"未经监理人书面指令，任何工程不得按计日工施工；接到监理工程师按计日工施工的书面指令，承包人也不得拒绝。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]