[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892215,578,1,"单选题","预算定额是在（ ）的基础上经综合扩大。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","概算定额",false,{"key":16,"text":17,"correct":14},"B","估算指标",{"key":19,"text":20,"correct":21},"C","施工定额",true,{"key":23,"text":24,"correct":14},"D","材料消耗量定额","预算定额是在施工定额的基础上经综合扩大，通过一定的计算方法编制出来的。它是按分项工程和结构构件的要求，以一定产品单位来规定劳动力、材料和机械的消耗数量。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]