[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892214,578,1,"单选题","（ ）是在建筑安装工人的正常施工条件下，完成单位合格产品的劳动力、材料、机械消耗的数量标准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工定额",true,{"key":16,"text":17,"correct":18},"B","预算定额",false,{"key":20,"text":21,"correct":18},"C","概算定额",{"key":23,"text":24,"correct":18},"D","估算指标","施工定额是在建筑安装工人的正常施工条件下，完成单位合格产品的劳动力、材料、机械消耗的数量标准。它是施工单位组织生产、编制施工阶段施工组织设计、签发任务单、计算计件工资、进行经济核算的依据。定额水平是先进的，但各个企业的施工定额不一定相同。在某种意义上说，企业的施工定额应该是保密的。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]