[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892213,578,1,"单选题","联合试运转费以定额建筑安装工程费为基数，按（ ）的费率计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.03%",false,{"key":16,"text":17,"correct":18},"B","0.04%",true,{"key":20,"text":21,"correct":14},"C","0.05%",{"key":23,"text":24,"correct":14},"D","0.07%","联合试运转费是指建设项目的机电工程，按照有关规定标准，需要进行整套设备带负荷联合试运转所需的全部费用，不包括应由设备安装工程费中开支的调试费用。联合试运转费以定额建筑安装工程费为基数，按0.04%的费率计算。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]