[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892205,578,1,"单选题","利润指施工企业完成所承包工程获得的盈利，按定额直接费及措施费、企业管理费之和的（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7.42%",true,{"key":16,"text":17,"correct":18},"B","7.41%",false,{"key":20,"text":21,"correct":18},"C","7.44%",{"key":23,"text":24,"correct":18},"D","7.43%","建筑安装工程费包括直接费、设备购置费、措施费、企业管理费、规费、利润、税金和专项费用。其中，利润是指施工企业完成所承包工程获得的盈利，按定额直接费及措施费、企业管理费之和的7.42%计算。",{"id":6,"name":27,"category":28,"favorite":29},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]