[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892187":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892187,577,2,"多选题","下列关于建筑电气项目的附属工程计量规则，正确的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","铁构件按名称.材质.规格，按设计图示尺寸以质量“kg”计算",true,{"key":16,"text":17,"correct":14},"B","凿槽按名称.类型.填充（恢复）方式.混凝土标准按设计图示尺寸以长度“m”计算",{"key":19,"text":20,"correct":14},"C","人（手）孔防水按名称.规格.类型.防水材质及做法等按设计图示尺寸以长度“m”计算",{"key":22,"text":23,"correct":14},"D","管道包封按名称.规格.类型.混凝土强度等级，按设计图示数量“个”计算",{"key":25,"text":26,"correct":27},"E","人（手）孔砌筑按名称.规格.类型.混凝土强度等级，按设计图示以长度“m”计算",false,"ABCD","知识点:建筑电气项目计量规则。管道包封、人（手）孔砌筑按名称、规格、类型、混凝土强度等级，按设计图示数量“个”计算。参见教材P249。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]