[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892156":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892156,577,2,"多选题","下列属于BIM技术在发承包阶段应用的包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单编制",true,{"key":16,"text":17,"correct":18},"B","成本计划管理",false,{"key":20,"text":21,"correct":14},"C","最高投标报价编制",{"key":23,"text":24,"correct":18},"D","设计概算的编审","AC","建设项目发承包阶段是BIM应用最集中的环节之一，主要包括工程量清单编制、最高投标报价编制、投标限价编制等。成本计划管理属于施工阶段的应用。设计概算的编审属于设计阶段的应用。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]