[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892155":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892155,577,2,"多选题","依据《通用安装工程工程量计算规范》（GB50856—2013）的规定，中压锅炉及其他辅助设备安装工程量计量时，以“只\"为计量单位的项目有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","省煤器",false,{"key":16,"text":17,"correct":18},"B","煤粉分离器",true,{"key":20,"text":21,"correct":18},"C","暖风器",{"key":23,"text":24,"correct":14},"D","旋风分离器","BC","省煤器以“t”为计量单位。煤粉分离器以“只\"为计量单位。暖风器以“只\"为计量单位。旋风分离器以“t”为计量单位。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]