[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892138":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892138,577,2,"多选题","根据《通用安装工程工程量计算规范》，属于安装专业措施项目的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","焊接工艺评定",true,{"key":16,"text":17,"correct":14},"B","工程系统检测.检验",{"key":19,"text":20,"correct":14},"C","吊装加固",{"key":22,"text":23,"correct":24},"D","环境保护",false,{"key":26,"text":27,"correct":24},"E","临时设施","ABC","知识点:安装工程措施项目清单。选项D、E属于安全文明施工及其他措施项目。参见教材P41～43。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]