[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892137":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892137,577,2,"多选题","编制工程量清单时，安装工程工程量清单计量根据的文件包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","经审定通过的项目可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","国家或省级.行业建设主管部门颁发的现行计价依据和办法",true,{"key":20,"text":21,"correct":18},"C","经审定通过的施工组织设计",{"key":23,"text":24,"correct":18},"D","经审定通过的施工图纸",{"key":26,"text":27,"correct":14},"E","经批准的项目建议书","BCD","知识点:安装工程分部分项工程工程量清单。工程量计算除依据《安装工程计算规范》中的各项规定外，还可依据以下文件编制：①国家或省级、行业建设主管部门颁发的现行计价依据和办法。②经审定通过的施工设计图纸及其说明、施工组织设计或施工方案、其他有关技术经济文件。③与建设工程有关的标准和规范。④经审定通过的其他有关技术经济文件。参见教材P38～39。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]