[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892091":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892091,577,2,"多选题","根据《通用安装工程工程量计算规范》，电力电缆安装工程计量单位正确的为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电力电缆、控制电缆，m",true,{"key":16,"text":17,"correct":18},"B","电缆保护管，个",false,{"key":20,"text":21,"correct":14},"C","电力电缆头，个",{"key":23,"text":24,"correct":18},"D","防火隔板，个","AC","本题考查的是建筑电气工程工程量计算。（1）电力电缆、控制电缆按设计图示尺寸以长度“m”计算（含预留长度及附加长度）。（2）电缆保护管、电缆槽盒、铺砂、盖保护板（砖）按设计图示尺寸以长度“m”计算。（3）电力电缆头、控制电缆头按设计图示数量以“个”计算。（4）防火隔板按设计图示尺寸以面积“m2”计算；防火涂料按设计图示尺寸以质量“kg”计算。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]