[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892083":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892083,577,2,"多选题","下列关于《2017安装预算定额》第十二册《刷油、防腐蚀、绝热工程》内容正确的为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","喷射除锈Sa3级，按人工、材料和机械乘以系数0.9",false,{"key":16,"text":17,"correct":18},"B","手工和动力工具除锈按St2标准确定，如按St3标准定额乘以系数1.10",true,{"key":20,"text":21,"correct":18},"C","通风管道绝热分材质、绝热层厚度以m2计量，按风管净面积计算",{"key":23,"text":24,"correct":14},"D","玻璃丝布、塑料布保护层定额按缠裹一层编制，缠裹两层其工程量乘以1.5","BC","本题考查的是《2017安装预算定额》第十二册《刷油、防腐蚀、绝热工程》。手工和动力工具除锈按St2标准确定。变更级别标准时需乘以系数，如按St3标准定额乘以系数1.10。喷射除锈按Sa2.5级标准确定。若变更级别标准，Sa3级定额乘以系数1.1，Sa2级定额乘以系数0.9。通风管道绝热分材质、绝热层厚度以m2计量，按风管净面积计算。玻璃丝布、塑料布保护层定额按缠裹一层编制，缠裹两层其工程量乘以2。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]