[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892073":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892073,577,2,"多选题","卫生器具交工前应做试验为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","灌水试验",false,{"key":16,"text":17,"correct":18},"B","通水试验",true,{"key":20,"text":21,"correct":18},"C","满水试验",{"key":23,"text":24,"correct":14},"D","冲洗和消毒","BC","本题考查的是给排水、采暖、燃气工程施工技术。承压管道系统和设备在隐蔽前必须做灌水试验。给水系统交付使用前必须进行通水试验并做好记录。生活给水系统管道在交付使用前必须冲洗和消毒。卫生器具交工前应做满水和通水试验。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]