[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892070":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892070,577,2,"多选题","投标人投标报价时应应按照招标人提供的金额填写，不得变动的费用有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":14},"B","材料暂估价",{"key":19,"text":20,"correct":21},"C","计日工",false,{"key":23,"text":24,"correct":21},"D","总承包服务费","AB","本题考查的是安装工程工程量清单计价。投标人对其他项目费投标报价时应遵循以下原则：①暂列金额应按照招标人提供的其他项目清单中列出的金额填写，不得变动。②暂估价不得变动和更改。③计日工应按照招标人提供的其他项目清单列出的项目和估算的数量，自主确定各项综合单价并结合自身的用工价格水平计算费用。④总承包服务费应根据招标人在招标文件中列出的分包专业工程内容和供应材料、设备情况，按照招标人提出的协调、配合与服务要求和施工现场管理需要自主确定。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]